Piti, Guam, October 8, 2026: The Port Authority of Guam continues to move cargo and maintain its vessel sequence following last Friday’s high wind incident, completing operations for the Matson Lurline and Galaide while beginning cargo operations for the APL Oceania today.

The APL Oceania secured its first line at 10:58 a.m. and is being serviced using Gantry Crane 4 and ship’s gear. Its arrival follows the completion of Lurline operations earlier this morning and the departure of the Galaide at 11:05 a.m. The Torm Thunder fuel tanker also arrived at the Port at 9:00 a.m., marking another day of active vessel movements at Guam’s commercial seaport.

“Today’s vessel activity demonstrates the commitment of our employees and shipping partners to keeping Guam’s supply chain moving,” General Manager Rory J. Respicio said. “We have completed the Lurline and Galaide operations, welcomed the APL Oceania and continued accommodating essential fuel deliveries, all while working to restore our full crane capacity. Our operational plan is moving forward, and our teams remain focused on serving every vessel safely and efficiently.”

The Lurline discharged 476 containers, consisting of 285 full imports and 191 transshipments, including two empty containers. The vessel also discharged 221 breakbulk units, comprising 90 pieces of heavy equipment and 131 automobiles.

The completion of Lurline operations allowed the Galaide, which had been docked at the Port since October 1, to receive five transshipment containers it had been awaiting. The Galaide completed its outbound operations with 13 containers, consisting of seven exports and six transshipments, along with one privately owned vehicle (POV) export.

Since Monday, the Port has released 395 containers and 237 breakbulk units into the community through its gatehouse. The breakbulk cargo includes 81 pieces of heavy equipment, 150 automobiles and six units of general cargo.

Meanwhile, recovery efforts on the Port’s gantry cranes continue. Gantry Crane 5 has been returned to the rail system and remains under repair and technical assessment. Gantry Crane 6 is also back on the rails and was successfully boomed down yesterday afternoon for further assessment. Repairs are now being made to Gantry Crane 6 so it can be prepared for re-certification and inspection on Saturday.

The Port continues coordinating with Matson, its gantry crane preventive maintenance contractor, and Smithbridge, which Matson brought in to assist with recovery operations. Port employees remain actively engaged in the repairs, inspections and assessments necessary to safely restore the remaining cranes to service.

“Operating with only one gantry crane has extended vessel working times by approximately one day compared with a typical call, and that has created some schedule movement in the vessel sequence,” Respicio said. “We are not minimizing that impact. At the same time, cargo continues to move through the terminal, and based on current operations we do not anticipate the vessel timing adjustment to materially affect the release of cargo through the gatehouse and into the community.”

The Port will continue providing updates as vessel operations and gantry crane recovery efforts progress.